Broadband Update 11/21/2019

Printer friendly

We have completed our drop bid and have awarded the new Otis contract to Sertex. We are happy to have them continue to be our contractor as we have gotten nothing but excellent response form our customers about their work. The new hut at the Otis Firehouse is up and running. We are currently doing installs in Phase 6 at the rate of 6 per day and it is our hope to have two additional crews in December so we will be doing 12 per day. Phase 7 splicing and testing is close to completion and we hope to have that turned over to us shortly. We will be getting a projection shortly on completion of the other Cases and will update the website as soon as we get that information.